August 2008
Visitor Center Dedication
Promontory Mound Dedication
Central Promontory Mound: "Topping Off Ceremony"
Visitor Center metal roof, walls, window system, drywall, finishes, paving & parking
Central Plant masonry, roof & plant completion
Central Promontory topsoil & irrigation
Bid prep for phase 2 steel
July 2008
Central Plant Masonry
Completion of Gallery Building Concrete
East Wing Floor Slab
Completion of Promontory Earthwork
Parking Lot Final Grading
Visitor Center Stud Walls
Visitor Center Metal Roof
June 2008
Central Plant Floor Slab
Central Plant Masonry
Gallery Building 1st Floor Concrete Walls
Hall of People Slab
East Wing Grade Beams
Truck Dock Waterproofing
Completion of Major Underground Utilities
Completion of Visitor Center Structural Steel
Completion of Visitor Center Structural Wood Beams and Deck
Visitor Center Finish Floor Topping Slab
Visitor Center Metal Stud Framing
Visitor Center Roof Insulation
May 2008
Tunnel light fixtures
Hall of People Slab
Central Plant Slab
Central Plant masonry
Visitor Center Structural Steel
Visitor Center Wood Framing
East Wing Grade Beams
Completion of Major Site Utilities
Continuation of Promontory Earthwork
April 2008
Promontory reinforced baskets
Promontory Earthwork
Visitor Center Floor Slab
Hall of People Grade Beams
Central Plant Underground
Central Plant Grade Beams
Tunnel Floors
March 2008
Promontory Trench Drain
Promontory Earthwork
Tunnel Lights and Floor
Loading Dock Walls
Central Plant Slab
Hall of People Grade Beams
East Wing Piers
Site Water & Sewer Lines
February 2008
Gallery Building loading dock
Central Plant foundation & storm sewer
West Passage Tunnel floor & endwalls
Central Promontory earthwork
Visitor Center building pad
Site Utilities storm sewer work
January 2008
Central Plant foundations
West Passage Tunnel backfill
Basement backfill
Visitor Center earthwork