December (2006)
Pier Drillling
November (2006)
Re-grading of slopes in preparation for erosion control seeding
Planting of erosion control
Imported soil for backfilling the basement
Received bids for Gallery Building and West Passage Tunnel concrete, waterproofing, plumbing, & electrical
Main parking lot was brought up to subgrade
On-going import of Promontory soil
September & October (2006)
Placed and compacted approximately 70,000 Cubic Yards of soil that will be used for the Great Promontory’s core earth structure
Began placing soil for the main parking lot and the Courtyard of the Winds
Oklahoma Energy Resource Board (OERB) removed all stockpiled oil field rubble from the property
August (2006)
Continued hauling in soil for the Great Promontory
Finished the initial grading required by the early site package
Completed the site clearing
Completed initial gravel base for the entrance road to the future loading dock
Began placing soil for the base of the Great Promontory
April - July (2006)
Initial site clearing of brush, trees, concrete rubble, tires, pipe, etc.
Searching and locating previously abandoned and buried oil wells
Plugging the located oil wells to current standards (plugging by Oklahoma Corporation Commission)
Basement excavation for the Gallery Building
Removal of abandoned utility line that passed through the basement area
Construction of the entry road base, which will eventually lead to the parking lot
Installation of the south barrier fencing
Construction and set-up of Centennial Builders' jobsite trailer complex
Shaping of the base of the Great Promontory
Cutting down the existing mound to subgrade level for the Courtyard of Nations
Erosion control
Soil Import and stockpiling for construction of the Great Promontory